REPORT NO: - 05
MONTH: - jan 2007 E.C. CONT. AGR. NO. -
DATE OF REPORT: 30/04/2007 E.C
PROJECT: high school
LOCATION: wortej/ tenta/ EMPLOYER: education BUREAU
CONSULTANT: ANRS, construction & Housing Agency
CONTRACTOR: Kihisen G/Hawariya B.C
1. CONTRACT SUMMARY
DATE OF SIGNATURE: July 17/ 2014 G.C
CONTRACT VALUE OF MAIN AGREEMENT BIRR 4,819,572.58 (+vt)ETB
SUPPLEMENTARY AGREEMENT BIRR -
VARIATION BIRR _________
TOTAL AMOUNT BIRR 4,819,572.58 (+vt)ETB
CONTRACT TIME 210 cal. day
MOBILIZATION TIME 10
COMMENCEMENT DATE JULY 27th 2014 G.C
COMPLETION DATE Jan.27 / 2015 G.C
ADDITIONAL TIME GIVEN _
EXTENSION OF TIME APPROVED
REVISED COMPLETION DATE . TIME ELAPSED IN DAYS 153 __
TIME ELAPSED IN % 72.86%_____
PERCENTAGE OF WORK EXECUTED 26.72%_________ PAYMENT CERTIFIED IN BIRR _____ PAYMENT CERTIFIED IN % ______